JEFFERSON CITY − The following is a list of general highway maintenance and construction work planned by the Missouri Department of Transportation in the mid-Missouri area Jan. 1–7. Weather conditions may postpone the scheduled work. Many projects will include lane closures that could cause delays.
MoDOT reminds drivers to buckle up, slow down, follow posted signs, and drive safely through work areas.
All counties
Moving operations such as mowing, brush cutting, and pavement repair continue in various locations. Motorists should travel with care and be alert for slow-moving equipment.
Boone County
Route K – Roadside work planned Jan. 2-5 from Route KK to where state maintenance ends. One lane will remain open, and crews will flag traffic through the work zone.
Route N – Roadside work planned Jan. 2-5. One lane will remain open, and crews will flag traffic through the work zone.
Interstate 70 – Bridge construction continues for the new Rocheport Bridge near mile marker 115. The project is scheduled for completion in December 2024.
Callaway County
Route EE – Culvert pipe replacements planned Jan. 3. All lanes will be closed between County Roads 1024 and 1006, 8 a.m. to 3 p.m.
Route B – Culvert pipe replacements planned Jan. 4. All lanes will be closed between Route N and Kelsch Lane, 8 a.m. to 5 p.m.
Camden County
U.S. Route 54 – Culvert pipe replacements planned Jan. 3 at Bumper Hill Road. One lane will remain open, and crews will flag traffic through the work zones.
Route N – Roadside work planned Jan. 2-5. One lane will remain open, and crews will flag traffic through the work zone.
Cole County
Route B – Culvert pipe replacements planned Jan. 2-4 from Osage Riverview Drive to Upper Bottom Road. One lane will remain open, and crews will flag traffic through the work zones.
Success! An email has been sent to with a link to confirm list signup.
Error! There was an error processing your request.
Cooper County
I-70 – Bridge construction continues for the new Rocheport Bridge near mile marker 115. The project is scheduled for completion in December 2024. main open, and crews will flag traffic through the work zones.
Maries County
Route 133 – Culvert pipe replacement planned Jan. 2-5 in the city limits of Belle. One lane will remain open, and crews will flag traffic through the work zone.
Route P – Culvert pipe replacement planned Jan. 2-5 at County Road 440. One lane will remain open, and crews will flag traffic through the work zone.
Route 28 – Bridge replacement continues at the Dry Fork Creek Bridge. The road is closed to all traffic and a signed detour is in place. The project is scheduled for completion in April 2024.
Phelps County
Route 63 – Culvert pipe replacement planned Jan. 2 – 4, 1.5 miles north of Yancy Mills. One lane will remain open, and crews will flag traffic through the work zone.
I-44 – Road resurfacing and reconstruction continues from Exit 186 in Rolla to Exit 195 in St. James. Expect around-the-clock lane closures from U.S. Route 63 to Missouri Route 68. An 11-foot width restriction is in place. The project is scheduled for completion in late September 2024.
Pulaski County
Missouri Route 133 – Culvert pipe replacement planned Jan. 2-5 south of Route C. One lane will remain open, and crews will flag traffic through the work zone.
Route 17 – Roadside work replacement planned Jan. 2-5, from Route K to the city of Crocker. One lane will remain open, and crews will flag traffic through the work zone.
Route DD – Roadside planned Jan. 2-5, 1 mile east of Bagnor Road. One lane will remain open, and crews will flag traffic through the work zone.
Route DD – Culvert pipe replacement planned Jan. 3, 1 mile east of Buttercup Road. One lane will remain open, and crews will flag traffic through the work zone.
I-44 – Bridge rehabilitation continues at the Roubidoux River Bridge. The project is scheduled for completion in April 2024.
I-44 – Bridge rehabilitation continues at the Big Piney River Bridge. One lane will remain closed for the duration of the project between Exits 163 and 169. The project is scheduled for completion in April 2024.